How an Aerospace Parts Manufacturer Saved ₹14 Lakhs/Month

Ending the Third Shift with Leanworx

An aerospace components manufacturer operating 40 CNC machines across three 8-hour shifts was running 24 hours a day, yet spindle utilization averaged only 30%. With limited visibility into actual machine performance, significant productive capacity was going unused. Leanworx enabled real-time spindle utilization and downtime tracking, helping the manufacturer increase utilization to 64%, eliminate the third shift, and save ₹14 lakhs every month without additional CapEx or hiring.

₹14L Monthly Savings
30% → 64% Spindle Utilization
40 CNC Machines