How an Automotive Parts Manufacturer Saved ₹15.6 Lakhs per Month with Leanworx

A Tier-2 automotive parts manufacturer was losing nearly 3 hours of productive time every day due to untracked machine downtime during shift changes. Across 39 CNC machines operating three 8-hour shifts, these delays resulted in a 12% reduction in daily output. Discover how Leanworx helped bring visibility to hidden shift-change losses and improve manufacturing productivity.

₹15.6L Monthly Savings
39 CNC Machines
12% Daily Output Loss Identified
Download Case Study

Free PDF Download · No Registration Required

CNC machine manufacturing operations – Leanworx shift change downtime case study
INDUSTRY 4.0 Every Shift Counts. Every Minute Matters.
Eliminating Downtime at Shift Change PDF Case Study · Free Download